Warwick Highway Weekly Log Sept. 24 - 30, 2012 Mon. Sept. 24 Removed two dead animals in road on Athol Rd. Installed new hydraulic hose on Backhoe Continued grading and rock raking of Old Winchester Rd. Continued to do finish work on Hastings Heights Rd. drainage project Tues. Sept. 25 Crushed dumpsters at transfer station Graded and rock raked Old Winchester Rd., W. Rum Brook Rd. and started Gale Rd. Completed finish work on Hastings Heights Rd. drainage project Wed. Sept. 26 Entire crew went to equipment show in Fitchburg Thurs. Sept. 27 Graded and rock raked Beech Hill Rd. Dug out rock on side of Orange Rd. that was going to impede plowing operations Cleaned up beaver debris on Hockanum Rd. Completed two Chapter 90 reimbursement requests to have signed and mailed in to Mass DOT Fri. Sept. 28 Dug out culverts on various roads in town Hauled 6 loads of old asphalt to G&S Lyman's pit in Orange Went to Orange for supplies