Warwick Highway Weekly Log July 1 - 7, 2013 Mon. July 1 Worked on highway dept. end of year reports HMA patched Hastings Heights Rd. Met with Lane Construction to go over Hastings Heights Rd. paving project Picked up trash at Police Station for Police Chief Put metal on ground into metal dumpster and crushed dumpsters at transfer station Went to Orange for supplies Tues. July 2 Repaired washouts on various roads Checked all roads for storm damage Worked on making repair to Grader tilting console panel Received report of tree down on Wendell Rd. - tree removed Wed. July 3 Repaired more washouts on various roads Dug out culverts on various roads Went to C.N. Wood in Whateley to discuss Grader repair and get informational service bulletin Continued with highway end of year reports Thurs. July 4 Holiday Fri. July 5 Larry and Tim on day off Checked on beaver problem areas in town