Warwick Highway Weekly Log July 18 - 24, 2011 Mon. July 18 Bill on vacation all week Swept Richmond Rd. Crushed dumpsters at transfer station Replaced swivel portion of seat in Backhoe Fixed washout and dirt potholes on Richmond Rd. Delivered culvert pipe to 3 jobs on Northfield Rd. Dealt with brush complaint on Pine St. Tues. July 19 Replaced culvert # 33 on Northfield Rd. before the old Spooner Rd. Wed. July 20 Replaced culvert # 38 on Northfield Rd. just west of Flower Hill Rd. Went to Hubbardston for Backhoe part Thurs. July 21 Tim on vacation day Worked on ditch line on Royalston Rd. Fri. July 22 Dug out rocks on Northfield Rd. just east of Flower Hill Rd. Cleaned up around culvert jobs done on Northfield Rd. earlier in the week Met with Verizon contractors who rerouted the underground cable on Northfield Rd. by Leland Hill Rd. to accommodate our culvert replacement Repaired leaking hydraulic fitting on backhoe