Warwick Highway Weekly Log July 11 - 17, 2011 Mon. July 11 Began patching Richmond Rd. in preparing for crumb rubber application Bill Lyman continued working on highway garage roof Worked on end of year reports Tues. July 12 Cut and chipped up downed trees and branches on various roads from previous storms Crushed dumpsters at transfer station Made welding repair to truck # 4 dump body subframe Checked roads for yellow ribbons relating to tree hearing on Wed. night Met with Ron from All-States Asphalt about Richmond Rd. and the 20% crumb rubber application Wed. July 13 Continued patching Richmond Rd. with HMA Did some clean up work on Richmond Rd. Cleaned up garage area Met with David Young to go over highway issues Tim had tree hearing at town hall in evening Thurs. July 14 Continued patching Richmond Rd. with HMA Filled out Conservation Commission permit paperwork Went to Whateley for Backhoe parts Fri. July 15 Finished patching Richmond Rd. Cleaned up Richmond Rd. for finish sweep Community Service people picked up trash on Athol Rd. Tim on vacation day