Warwick Highway Weekly Log Feb. 21 - 27, 2011 Mon. Feb. 21 Holiday Called in personnel to sand all paved roads at 2 A.M. - began finish plowing and sanding at 9 A.M. - called in private contractors at 9 A.M. - went home at 1:45 P.M. - 2" of snow Tues. Feb. 22 Jim on comp day Sanded all dirt roads due to slippery conditions Cleaned up tree damage from weekend wind storm Went to Whateley for parts for Backhoe Went to Orange for parts Tim went to Select Board meeting Wed. Feb. 23 Cleared snow from village area Flipped cutting edge on truck # 1 plow Did complete service on Backhoe Tim went to Tri-County Supt. meeting in Westfield in afternoon Thurs. Feb. 24 Opened up E. Wilson Rd. to cabin for resident and sanded Pete's Tire came to install 4 new tires on Backhoe Replaced leaning wheel piston on Grader Washed and greased three trucks Fri. Feb. 25 Personnel came in at 3 A.M. to sand all paved roads - called in private contractors and began plowing all roads at 8 A.M. - began mixing with sleet and rain at 10 A.M. - private contractors sent home at 12 P.M. - re-scraped and sanded main roads at 12:30 P.M. - called in private contractors and began finish plowing of all roads and sanding of paved roads at 6:45 P.M. - went home at 11:30 P.M. - 7" of very heavy, wet snow, sleet, freezing rain and rain Sun. Feb. 27 Called in personnel at 6 A.M. - called in privates and began plowing all roads and sanding paved roads at 6:15 A.M. - went home at 11:45 - 4" of snow