Warwick Highway Weekly Log Oct. 15 - 21, 2012 Mon. Oct. 15 HMA patched Northfield Rd. and Mt. Grace Ave. Met with homeowner on Richmond Rd. about marked trees for cutting Repaired culvert headwall on Northfield Rd. Crushed dumpsters at transfer station Met with David Young on highway issues Tues. Oct. 16 Graded and rock raked Kirk Rd., N. Holden Rd., Hastings Pond Rd. and Flower Hill Rd. Measured up future work to be done on Athol Rd. and Hastings Heights Rd. Wed. Oct. 17 Graded and rock raked Bass Rd. and Buzzell Pl. Thurs. Oct. 18 Graded and rock raked last portion of Gale Rd. Patched various roads around town Fri. Oct. 19 Began switching truck # 3 over from a dump truck to a sander and redoing some of the wiring on the frame and rear lights Checked all roads for problems and adjusting all signage